Adjustment done, Works Completed, Tunnel handed over to NR

Posted by [email protected] on March 17, 2015 at 6:00 AM

Update 16th Mar'2015:

The adjustment of height and stagger was completed on Sunday 15th Mar. The expansion joints were also checked and final regulated. This was followed by final check with a pan-unit and tunnel clean-up works.

Officials from NR & F+F also visited the site and the response was encouraging.

The system is now ready for commissioning.

The earths will be removed on 17th Mar morning and the system would be switched on with 25kV feed. The train testing is then planned in the afternoon with 2 units of Bombardier Class 387 trains.


Categories: Progress Update

Post a Comment

Oops!

Oops, you forgot something.

Oops!

The words you entered did not match the given text. Please try again.

Already a member? Sign In

0 Comments

Oops! This site has expired.

If you are the site owner, please renew your premium subscription or contact support.